Tuesday, 19 March 2013

Project update - 10

 
Project update - 10
 
This week we marked the end of the design and creation stages of the project with the completion of the storyboard and the levels James and I were assigned to create (printscreens of the level will be added later). Unfortunately we are still behind on the project due to several holidays during the project lifecycle, we currently need to get the game beta tested and then sign off. We still have plenty of time in order to complete the last tasks so the current setback wont be too much of an issue.
 
 
 
The current gant chart.




An example of our concept art.

Tuesday, 12 March 2013

Project update - 8

Project update - 8
 
This week I marked the end of the design stage by completing the games storyboard and layout. The group is currently behind schedule due to some unforeseen setbacks (holidays). But creation of the game has already begun and we have managed to save a lot of time as we had spare time
inbetween making designs so we could begin creation of the actual game alongside the design stage.
 
 
According to the gant chart we are behind schedule, however, the time allocated for feedback and signing off shouldn't take the amount of days stated, so we will still make the deadline.
 
 
The current storyboard.